Approximation Algorithms for Two-stage Flexible Flow Shop Scheduling Subject to Release Dates
Wang Hui, Lu Xiwen(Institute of Applied Mathematics of East China University of Science and Technology, Shanghai 200237, China.)
Abstract:
Consider a two-stage flexible flow shop scheduling problem subject to release dates. Based on the idea of solving the flow-shop problem and parallel machine problem, we provide two approximation algorithms H(R) and H(MRJ'). The worst-case performance ratios for the two algorithms are proven to be 3 - 1 5 1/ m and 5/2-1/m respectively. We discuss the tightness of the bound and do numerical simulation to analyze the approximation performance ratio between the algorithm and the optimal solution.[著者文摘]
Key words:
Operations research, flexible flow shop, release dates, scheduling, performance ratio